Calculating the Load 5.13 

 

Instructions: A work center has the following open and planned orders for week 4. Calculate the total standard time required (load). 

 

Work Center Orders  

  

Order Quantity 

Setup Time (hours) 

Run Time (hours/piece) 

Total Time (hours) 

Released Orders: 120 

300 

1.00 

0.10 

  

340 

200 

2.50 

0.30 

  

Planned Orders: 560 

300 

3.00 

0.25 

  

780 

500 

2.00 

0.15 

  

Total Time (standard hours)